Smart Electrical Power Distribution Centre

Planning

SEPDC Planning July 2011 - July 2013

Task Type Start End
WP1 Project Management Workpackage 01/07/2011 30/07/2013
D1.1 Quality Assurance plan Deliverable 01/07/2011 30/12/2011
D1.2 Risk Management plan Deliverable 01/07/2011 30/12/2011
MS1 Hand over of Quality Assurance and Management plan Milestone 01/01/2012 13/01/2012
WP2 Detailed specifications and requirements Workpackage 01/07/2011 30/12/2011
D2.1 Approved list Deliverable 01/11/2011 30/12/2011
MS2 Approved specifications Milestone 01/01/2012 13/01/2012
WP3 Conceptual design Workpackage 01/11/2011 29/02/2012
D3.1 CAD Design Deliverable 01/11/2011 29/02/2012
D3.2 BOM List and electrical schematics Deliverable 01/11/2011 29/02/2012
MS4 PDR (Preliminary Design Review) Milestone 01/01/2012 13/01/2012
MS3 Acceptance of SEPDC Concept Milestone 01/02/2012 18/04/2012
WP4 Manufacturing of subsystems Workpackage 14/03/2012 01/11/2012
D4.1 Assembly of SEPDC Deliverable 14/03/2012 01/11/2012
D4.2 Emulation software Deliverable 14/03/2012 01/06/2013
D4.3 Single Rack test Deliverable 01/10/2012 01/11/2012
MS5 Workshop SEPDC no 1 Milestone 01/09/2012 02/09/2012
WP5 Assembly and integration of subsystems Workpackage 01/07/2012 01/02/2013
D5.1 FAT Report Deliverable 01/07/2012 01/02/2013
MS6 FAT Report Rack Milestone 01/02/2013 12/02/2013
MS7 Approval of RACK Milestone 15/02/2013 25/02/2013
D7.1 Dissemination in european technical media Deliverable 01/10/2013 10/02/2013
D7.2 SEPDC Website Deliverable 01/10/2011 10/02/2012
WP6 Commissioning and Demonstration Workpackage 01/03/2013 22/07/2013
D6.1 Commisioning report Deliverable 25/06/2013 29/06/2013